| | + | ==Module installation and connection procedure== |
| | + | |
| | + | #Connect the outputs. |
| | + | #Connect the inputs. |
| | + | #Connect the Can connector. |
| | + | #Configure the module using LT setup. |
| | + | #Apply power to the load |
| | + | #Check all equipment for proper operation. |
| | + | |
| | + | ==Module shut-off and deinstallation procedure== |
| | + | |
| | + | #Disconnect the power from the load |
| | + | #Disconnect the CAN connector. |
| | + | #Disconnect the inputs. |
| | + | #Disconnect the outputs. |