| Line 80: |
Line 80: |
| | ==Module installation and connection procedure== | | ==Module installation and connection procedure== |
| | #Install the module in the switchboard on the DIN rail and fix it with the special latch on the module base. | | #Install the module in the switchboard on the DIN rail and fix it with the special latch on the module base. |
| | + | #Connect the X1 connector. |
| | #Connect the CAN connector. | | #Connect the CAN connector. |
| − | #Connect the X1 connector.
| |
| | #Configure the module using LT setup. | | #Configure the module using LT setup. |
| − | #Apply power to the load.
| |
| | #Check all equipment for proper operation. | | #Check all equipment for proper operation. |
| | | | |
| | ==Module shut-off and deinstallation procedure== | | ==Module shut-off and deinstallation procedure== |
| − | #Disconnect the power from the load. | + | #Disconnect the CAN connector. |
| | #Disconnect the X1 connector. | | #Disconnect the X1 connector. |
| − | #Disconnect the CAN connector.
| |
| | #Remove the module from the DIN rail, releasing the latch at the bottom of the module base. | | #Remove the module from the DIN rail, releasing the latch at the bottom of the module base. |
| | | | |